BLHS: Expansion & intersection update, June 2026

An aerial view of a Bonney Lake High School site plan for improved turf fields and a new building addition.

Great work continues on the Bonney Lake High School Expansion & Intersection Improvement construction project. The following updates were given at the June 15 Bond Oversight Committee meeting: 

Expansion:

  • Permit received for 500 Wing Piping Replacement
  • Scheduled to start demo, wall construction and 500 wing piping in the summer
  • Construction sequencing, paths of travel, safety and communication agreed by all parties
  • SEPA submitted. Comment period ended June 1.

Intersection:

  • Permit comments received and responded to
  • Project schedule pushed to Summer 2027 due to permit timing

See the latest updates in the June 15 Bond Oversight Committee Meeting presentation.