Great work continues on the Bonney Lake High School Expansion & Intersection Improvement construction project. The following updates were given at the March 23 Bond Oversight Committee meeting: 

Expansion:

  • Building construction documents submitted to City of Bonney Lake for permitting
  • Design development drawings complete and ready to present to the School Board
  • Construction documents in progress
  • Detailed construction sequencing in development
  • Joint outreach event planned for May with Skanska

Intersection:

  • Design complete
  • Permit submitted. Awaiting comments from the City of Bonney Lake
  • Updated Traffic Impact Analysis underway

See the latest updates in the March 23 Bond Oversight Committee Meeting presentation.